Construction Delays: How to Protect Your Rights

UPDATED: Jul 12, 2023Fact Checked

Get Legal Help Today

Find the right lawyer for your legal issue.

secured lock Secured with SHA-256 Encryption

Jeffrey Johnson

Insurance Lawyer

Jeffrey Johnson is a legal writer with a focus on personal injury. He has worked on personal injury and sovereign immunity litigation in addition to experience in family, estate, and criminal law. He earned a J.D. from the University of Baltimore and has worked in legal offices and non-profits in Maryland, Texas, and North Carolina. He has also earned an MFA in screenwriting from Chapman Univer...

Insurance Lawyer

UPDATED: Jul 12, 2023

Advertiser Disclosure

It’s all about you. We want to help you make the right legal decisions.

We strive to help you make confident insurance and legal decisions. Finding trusted and reliable insurance quotes and legal advice should be easy. This doesn’t influence our content. Our opinions are our own.

Editorial Guidelines: We are a free online resource for anyone interested in learning more about legal topics and insurance. Our goal is to be an objective, third-party resource for everything legal and insurance related. We update our site regularly, and all content is reviewed by experts.

UPDATED: Jul 12, 2023Fact Checked

Construction delays can cost not only time, but also money. So, when you enter into a building project, it is important to have a contract that outlines a deadline for completion as well as specifies what is to occur in the event of a delay. While the court may consider a delay in performance a material breach of a construction agreement, even if the contract does not specify a completion date, it is far better to clearly lay out the terms of your construction agreement to protect yourself.

Construction Law and Unreasonable Delays

When a contract does not specify a construction completion date, the court may consider an unreasonable delay to be a material breach. For example, in the case, International Production Specialists, Inc. v. Schwing America, Inc., No. 07-3632, 2009 Westlaw 276 7143 (7th Cir. September 2, 2009), the Seventh Circuit Court of Appeals determined that a 3 ½-year delay was a material breach of a construction agreement, even though the contract did not specify an end date. The Court based its decision on evidence, including project timelines, which indicated that the party commissioning the work had expected the project to take approximately 8 months.

In the Schwing case, the court specified that the party’s expectations and the materiality of the breach of the agreement should be determined in light of the circumstances as a whole, including the potential for normal construction delays, who is responsible for the delays, and what benefits the parties to the construction contract could reasonably expect.

Protecting Yourself Against Delays

While the Schwing case resulted in Schwing being permitted to cancel the contract with the builders who weren’t performing work in a timely or reasonable manner, this case is an extreme example.  Not every single construction delay will result in a court finding a material breach without a specified finish date. To protect yourself under construction law, establish a clear deadline in your contract. The deadline should provide a reasonable amount of time to complete the project, allowing for the fact that delays can occur even when no one is at fault.

Define Substantial Completion

Typically, it is common for the contract to specify that “substantial completion” must occur by a certain date. You should also specify in this agreement what substantial completion means, such as stating that the project must be at least 75 percent completed. The contract should also include a clause that extensions can be given for unforeseen delays at the discretion of the person who commissioned the building project. This ensures that when something unexpected happens, the builder will confer with the owner regarding how to proceed and won’t feel pressured to complete the impossible.

Adding a Liquidated Damages Clause

If a builder breaches a contract by not achieving substantial completion by the specified date, the builder can then be responsible for damages. In the event that damages cannot be specifically determined, a liquidated damage clause can be added to make clear in advance the penalties from the delay. Liquidated damage clauses are typically enforceable as long as the amount specified for damages is considered to be a reasonable assessment of losses rather than solely intended to punish the party in breach.

Owner Changes to the Project

When a contract specifies a date of completion, it is important for owners to know that if they make changes to the scope of the project or the work being done, the completion date may need to be altered as well. Typically, when a change is made after a construction contract is signed, this is referred to as a “change order,” and the change order may specify a new completion date or a deadline extension.

In order to ensure that the construction contract contains the necessary language and clauses to adequately protect your rights, it is best to consult with an attorney who specializes in construction law.

Case Studies: Construction Delays and Legal Protection

Case Study 1: John’s Construction Project

John entered into a construction agreement to build his dream home. The contract did not specify a completion date. However, after a 2-year delay, John considered it a material breach. By presenting evidence of project timelines and his expectations, John was able to successfully argue for a breach of contract.

Case Study 2: Sarah’s Deadline Extension

Sarah hired a contractor to renovate her restaurant. The contract specified a completion date, but unforeseen circumstances caused delays. Fortunately, Sarah had included an extension clause in the contract, allowing her to grant additional time for unexpected events. This provision protected her rights and ensured a fair resolution.

Case Study 3: Mark’s Liquidated Damages Clause

Mark contracted a construction company to build a commercial building. To protect himself from potential delays, Mark included a liquidated damages clause in the contract. When the contractor failed to achieve substantial completion by the specified date, Mark was entitled to receive predetermined compensation, avoiding lengthy legal battles.

Case Study 4: Owner Changes and Mark’s Change Order

During the construction of Mark’s commercial building, he decided to make significant changes to the project scope. These changes required a change order, which included a new completion date or a deadline extension. By documenting and communicating the modifications, Mark ensured that the revised contract protected his rights and the contractor’s obligations.

Get Legal Help Today

Find the right lawyer for your legal issue.

secured lock Secured with SHA-256 Encryption

Jeffrey Johnson

Insurance Lawyer

Jeffrey Johnson is a legal writer with a focus on personal injury. He has worked on personal injury and sovereign immunity litigation in addition to experience in family, estate, and criminal law. He earned a J.D. from the University of Baltimore and has worked in legal offices and non-profits in Maryland, Texas, and North Carolina. He has also earned an MFA in screenwriting from Chapman Univer...

Insurance Lawyer

Editorial Guidelines: We are a free online resource for anyone interested in learning more about legal topics and insurance. Our goal is to be an objective, third-party resource for everything legal and insurance related. We update our site regularly, and all content is reviewed by experts.

Get Legal Help Today

Find the right lawyer for your legal issue.

secured lock Secured with SHA-256 Encryption